The UBDC Hydel Channel Stage-III, at Pathankot will take off at RD 70000 (left) of UBDC Main Canal & will fall into the river Beas. The total cost of the project will be Rs. 650 crore.
For PH-I, there will be 3 units of 15 MW each and for PH-II, there will be 2 units of 15 MW each. Hence, the total generating capacity of the project will be 75 MW.
The site office has already opened at Pathankot. Soil investigation works, Topographical and Contour Survey are already completed at Site and the Land identification work is in progress. Bankable Detailed Project Report (DPR) will be ready by end Jan’07 and financial closure is targeted by end Feb’07.